Browse Section: Manholes, precast
Manholes, precast
Util vault, prcst concrete, 6" T, MH, power only, 10'x13'x7' D
| Item | Rate |
|---|---|
| Material | 6,465.76 / EA |
| Laborers, (Semi-Skilled) Foreman ($33.86/hour for 10.00 hours) | 338.57 / EA |
| Laborers, (Semi-Skilled) ($32.49/hour for 40.00 hours) | 1,299.68 / EA |
| Equip. Operators, Crane/Shovel ($44.51/hour for 10.00 hours) | 445.10 / EA |
| Equip. Operators, Oilers ($33.69/hour for 10.00 hours) | 336.90 / EA |
| CRANE, HYD, TRUCK MTD, 60 TON 115' BOOM ($111.02/hour for 10.00 hours) | 1,110.16 / EA |
| Other | 0.00 / EA |
| Total | 9,996.16 / EA |
| end of record | |