Comm Manhole 4'x4'x4' With Rack, French Drain Complete & Install
| Item | Rate |
|---|---|
| Material | 810.70 / EA |
| Electricians ($46.83/hour for 2.56 hours) | 119.81 / EA |
| Equip. Operators, Medium Foreman ($42.67/hour for 1.94 hours) | 82.69 / EA |
| Equip. Operators, Medium ($41.30/hour for 15.50 hours) | 640.38 / EA |
| Truck Drivers, Light ($31.72/hour for 7.75 hours) | 245.91 / EA |
| HYD EXCAV,CRWLR, 1.00CY BKT,LONG ($67.69/hour for 7.75 hours) | 524.72 / EA |
| LDR,FE, WH, 2.50 CY, ARTIC, 936E ($48.80/hour for 7.75 hours) | 378.27 / EA |
| REAR DUMP BODY, 8 CY,(30,000 GVW ($4.36/hour for 7.75 hours) | 33.79 / EA |
| TRK,HWY, 46,000 GVW, 6X4, 3 AXLE ($53.40/hour for 7.75 hours) | 413.95 / EA |
| Other | 0.00 / EA |
| Total | 3,250.22 / EA |