Browse Section: Rigid clear span frame with openings
Rigid clear span frame with openings
PESB, 26ga clrd rfg & sdg, 50'x80', 16'eave with 2-3'dr & 1-10, rgd clr span
| Item | Rate |
|---|---|
| Material | 25,450.89 / EA |
| Structural Steel Workers Foreman ($55.35/hour for 23.20 hours) | 1,284.34 / EA |
| Structural Steel Workers ($53.99/hour for 92.81 hours) | 5,010.71 / EA |
| Equip. Operators, Crane/Shovel ($44.51/hour for 23.20 hours) | 1,032.67 / EA |
| Equip. Operators, Oilers ($33.69/hour for 23.20 hours) | 781.63 / EA |
| CRANE, MECH, TRUCK MTD 125 TON, 260' BOOM ($187.01/hour for 23.20 hours) | 4,338.88 / EA |
| Other | 0.00 / EA |
| Total | 37,899.11 / EA |
| end of record | |