Browse Section: Perforated PVC, schedule 40

Perforated PVC, schedule 40

Piping, subdrainage, perforated PVC, 12" dia


Item Rate

Material6.95 / LF
Laborers, (Semi-Skilled) Foreman ($33.85/hour for 0.03 hours) 1.00 / LF
Laborers, (Semi-Skilled) ($32.49/hour for 0.12 hours) 3.85 / LF
Equip. Operators, Light ($38.90/hour for 0.03 hours) 1.15 / LF
LOADER/BH, WH, 0.80 CY, F/E BKT 30" DIPPER ($18.31/hour for 0.03 hours) 0.54 / LF
Other0.00 / LF

Total13.50 / LF