Browse Section: Binder course
Binder course
Asphaltic concrete pavement, highway, binder course, 1.5" thick
| Item | Rate |
|---|---|
| Material | 37.51 / TON |
| Laborers, (Semi-Skilled) Foreman ($33.85/hour for 0.01 hours) | 0.43 / TON |
| Laborers, (Semi-Skilled) ($32.49/hour for 0.09 hours) | 2.89 / TON |
| Equip. Operators, Medium ($41.30/hour for 0.04 hours) | 1.57 / TON |
| ASPHALT FINISHER, 10', WHEEL (WITH 19' SCREED EXT) ($92.02/hour for 0.01 hours) | 1.17 / TON |
| ROLLER, VIB, TANDEM, S/P 12 TON, 67" WIDE X 51" DIA ($58.51/hour for 0.01 hours) | 0.74 / TON |
| ROLLER, STATIC, S/P, 13 TON 84"WIDE, 11 TIRES ($24.57/hour for 0.01 hours) | 0.31 / TON |
| Other | 0.00 / TON |
| Total | 44.63 / TON |
| end of record | |