Caisson, 24" shaft,.444CY, wet gnd, for bell & concrete, 4' bell dia, open


Item Rate

Material36.53 / EA
Laborers, (Semi-Skilled) Foreman ($33.85/hour for 0.40 hours) 13.68 / EA
Laborers, (Semi-Skilled) ($32.49/hour for 1.21 hours) 39.38 / EA
Equip. Operators, Crane/Shovel ($44.51/hour for 0.40 hours) 17.98 / EA
Equip. Operators, Oilers ($33.69/hour for 0.40 hours) 13.61 / EA
Equip. Operators, Light ($38.90/hour for 0.40 hours) 15.72 / EA
PUMP, CENTRF, DEWATER, 6" DIA 1,100 GPM AT 40' HEAD ($26.02/hour for 0.40 hours) 10.51 / EA
HOSE, SUCTION/DISCHARGE,6" X 20' (WITH COUPLING, PER SECTION) ($0.33/hour for 0.40 hours) 0.13 / EA
HOSE, SUCTION/DISCHARGE,6" X 20' (WITH COUPLING, PER SECTION) ($0.33/hour for 0.40 hours) 0.13 / EA
DRILL, HORZ BORING, 36" DIA 30' TRACK (W/100' AUGER TRACK) ($40.20/hour for 0.40 hours) 16.24 / EA
Other0.00 / EA

Total163.92 / EA