Browse Section: Open style, machine drilled, wet ground

Open style, machine drilled, wet ground

Caisson, 48"dia,.465CY/LF, to 50'D, wet gnd, pulled case/pmp, open,mach dr


Item Rate

Material46.54 / VLF
Laborers, (Semi-Skilled) Foreman ($33.67/hour for 0.15 hours) 4.90 / VLF
Laborers, (Semi-Skilled) ($32.31/hour for 0.44 hours) 14.10 / VLF
Equip. Operators, Crane/Shovel ($44.26/hour for 0.29 hours) 12.88 / VLF
Equip. Operators, Oilers ($33.50/hour for 0.29 hours) 9.75 / VLF
Equip. Operators, Light ($38.69/hour for 0.15 hours) 5.63 / VLF
Pile Drivers ($47.13/hour for 0.29 hours) 13.71 / VLF
CRANE, HYD, TRUCK MTD, 25 TON 80' BOOM ($67.34/hour for 0.15 hours) 9.79 / VLF
PUMP, CENTRF, DEWATER, 6" DIA 1,100 GPM AT 40' HEAD ($25.88/hour for 0.15 hours) 3.76 / VLF
HOSE, SUCTION/DISCHARGE,6" X 20' (WITH COUPLING, PER SECTION) ($0.33/hour for 0.15 hours) 0.05 / VLF
HOSE, SUCTION/DISCHARGE,6" X 20' (WITH COUPLING, PER SECTION) ($0.33/hour for 0.15 hours) 0.05 / VLF
DRILL, HORZ BORING, 36" DIA 30' TRACK (W/100' AUGER TRACK) ($39.98/hour for 0.15 hours) 5.82 / VLF
Other0.00 / VLF

Total126.97 / VLF
end of record