Browse Section: Open style, machine drilled, wet ground

Open style, machine drilled, wet ground

Caisson, 30"dia,.182CY/LF, to 50'D, wet gnd, pulled case/pmp, open,mach dr


Item Rate

Material18.19 / VLF
Laborers, (Semi-Skilled) Foreman ($33.67/hour for 0.09 hours) 3.17 / VLF
Laborers, (Semi-Skilled) ($32.31/hour for 0.28 hours) 9.12 / VLF
Equip. Operators, Crane/Shovel ($44.26/hour for 0.09 hours) 4.17 / VLF
Equip. Operators, Oilers ($33.50/hour for 0.09 hours) 3.15 / VLF
Equip. Operators, Light ($38.69/hour for 0.09 hours) 3.64 / VLF
PUMP, CENTRF, DEWATER, 6" DIA 1,100 GPM AT 40' HEAD ($25.88/hour for 0.09 hours) 2.44 / VLF
HOSE, SUCTION/DISCHARGE,6" X 20' (WITH COUPLING, PER SECTION) ($0.33/hour for 0.09 hours) 0.03 / VLF
HOSE, SUCTION/DISCHARGE,6" X 20' (WITH COUPLING, PER SECTION) ($0.33/hour for 0.09 hours) 0.03 / VLF
DRILL, HORZ BORING, 36" DIA 30' TRACK (W/100' AUGER TRACK) ($39.98/hour for 0.09 hours) 3.76 / VLF
Other0.00 / VLF

Total47.71 / VLF
end of record