Browse our database
Top of Database» Site Work
»» Hazardous And Toxic Waste
»»» Asbestos Abatement - Method 4
»»»» Preparatory,Abatement And Post-Abatement Gen Req
»»»» Abatement In Isolated Work Area
»»»» Abatement In Semi-Isolated Area
»»»» Miscellaneous & Exterior Removal
»»»» Asbestos Removal
Asbestos Abatement - Method 4
| Item | Rate |
|---|---|
| Asbestos Abatement Notification Fees Detail | $ 1,714.29 / JOB |
| Asbestos Decon of Trucks & Equipment Mobilization Fees Detail | $ 2,571.42 / JOB |
| Remove and Return Office Furniture General, (SF of Office Floor) Detail | $ 0.40 / SF |
| Remove and Return Lighting Fixtures Detail | $ 25.17 / EA |
| HEPA Vac & Wet Clean, 6-11' Ceil SF of Floor, Wall, Ceiling Detail | $ 0.18 / SF |
| HEPA Vac & Wet Clean 12-15' Ceil Detail | $ 0.21 / SF |
| HEPA Vac and Wet Clean >15' Ceil 15'-Ceil>Detail | $ 0.33 / SF |
| Protect Carpeted Area, 2 Layers 6 Mil Poly Detail | $ 1.59 / SF |
| Separation Barrier, 2"X 4" @ 16", 1/2" Plywood Each Side, 8' High Detail | $ 4.07 / SF |
| Separation Barrier, 2"X 4" @ 16", 1/2" Plywood Each Side 12' High Detail | $ 4.59 / SF |
| Separation Barrier, 2"X 4" @ 16", 1/2" Plywood Each Side, 16'High Detail | $ 6.25 / SF |
| Personnel Decontamination Chamber Detail | $ 5.24 / SF |
| Waste Decontamination Chamber Detail | $ 5.16 / SF |
| Isolate Asbestos Work Area Floors Floor Area x 2 Layers 6 Mil Poly Detail | $ 0.64 / SF |
| Isolate Asbestos Work Area Wall/Ceil Wall Area x 2 Layers 4 Mil Poly Detail | $ 0.70 / SF |
| Wrap-Up General Office Furniture and Equipment with 1 Sheeting Laye Detail | $ 17.72 / EA |
| Wrap-Up Large/Complex Equipment 2 Layers of 6mm Sheeting Detail | $ 4.73 / SF |
| Set Up Port Asbestos Decon Facility Cost Amortized Over 10 Jobs Detail | $ 949.67 / EA |
| Set Up Int Custom Asbestos Decon Fac Interior Areas Detail | $ 439.81 / EA |
| Set Up Ext Custom Asbestos Decon Fac Weatherized Detail | $ 2,612.32 / EA |
| Limit reached, Search or navigate deeper | |